- How likely is it that you will know (or be given) every PI Point name you need to work with?

  1. How likely is it that you will know (or be given) every PI Point name you need to work with?

Unlikely unless you are very familiar with the naming conventions

2.    Your boss sees your great work and says that MixingTank2 should have the same display, how do you build out another display for the second mixing tank?

Start again and replicate the process you used for Tank 1, choosing the relevant PI Points

3.    Next week, you know that the products in your mixing tanks will change. How would you get this new information onto your display without the use of Asset Framework?

If save my display I could update it for a new time period next week.